Why Stepping into Our Future?
Most sacred Catholic places were built to last lifetimes. Indeed, numerous are the most beautiful and oldest structures in the places they inhabit, constructed long ago by people who used stone, brick, and massive timbers as a demonstration of the longevity of their faith.
But even the most solidly built Catholic churches require regular maintenance and repairs for them to remain for future generations. As time passes, roofs leak, foundations crack, heating and cooling systems fail and building codes / requirements change that require us to review our existing church conditions. The responsibility of providing a safe and secure environment for church members, staff, and visitors is a top priority for St. Patrick Church. Effectively identifying and managing risks and reducing hazards not only safeguards the welfare of all involved but also helps our church maintain an environment favorable to worship, fellowship, and spiritual growth.
As we all continue on this journey of Stepping into Our Future, we encourage you re-visit this section of our website to learn more about the project and to keep you informed of the construction progress, pictures and updates from Father Dennis. Most importantly, it is because of YOU that will make this project successful! Thank you for your support.
STAGE / PHASE 1.5
New front stairs/handrails, new raised upper landing to allow visitors to walk out of church, without having to step down. A new 20 x 50 storage will be created, under the upper landing, to be used for preparing church flowers, refrigeration storage and storage of holiday and Christmas decorations.
Start Date: Quarter 2 (Q2) 2025
Duration: 6 to 8 months
Impacts: Mass will still be held inside the church, but entrance will be by the new staircase between the narthex and the church hall. Elevator will be available for use.
STAGE / PHASE 2
Replacement of the granite retaining wall. Along the side of the Center, provide a pedestrian walkway from the back parking lot, leading up to a bridge crossing over to the upper landing.
Start Date: Q1 2026
Duration: 6 months
Impacts: TBD, Limited elevator access from exterior